Red Oak Drive Sanitary Sewer Lift Station Rehabilitation Project

Red Oak Lift Station Rehab Project Map

Project Summary

The City is rehabilitating the sanitary sewer lift station at 8491 Red Oak Drive to maintain reliable sewer service.

A portion of Red Oak Drive will be closed during construction.

Work includes:

  • Rehabilitation of the underground concrete pumping structure, including roadway excavation, pipe installation and concrete repairs.
  • Replacement of the lift station control panel located within the public right-of-way. 
  • Installation of a temporary bypass pumping system to maintain sewer service during construction.

Residents will notice above-ground pipes, temporary pumping equipment and periodic construction activity in the area. 

Timeline

Work is expected to begin June 10 and be completed in mid-July.